International news · 21 Oct 2026

Westinghouse to spend $1 billion on US LEU+ fuel plant

Westinghouse has begun building a plant in South Carolina to make fuel enriched to 5-8% uranium-235, with production due to start in 2030.

Westinghouse's Columbia fuel fabrication facilityPhoto: US Nuclear Regulatory Commission

Westinghouse Electric Company is investing about $1 billion in a new facility for low-enriched uranium plus (LEU+) fuel at its Columbia fuel fabrication site near Hopkins, South Carolina. Construction has begun, and production is scheduled for 2030.

Commercial light-water reactors typically use fuel enriched to up to 5% uranium-235; LEU+ fuel is enriched to between 5% and 8%. According to the company, it could let pressurised water reactors run 24 months between refuelling outages instead of 18, and support power uprates. The added capacity is also meant to support wider deployment of its AP1000 reactor.

Westinghouse's first LEU+ lead test assemblies were loaded into Unit 2 of the Vogtle plant in Georgia in April 2025, after being made at the Columbia facility under the EnCore fuel programme supported by the US Department of Energy. The Columbia plant, operating since 1968, makes fuel pellets, rods and assemblies and employs more than 1,200 people.