Uranium price at a record high: demand rising, supply lagging

The long-term contract price of uranium reached $98 per pound at the end of October, the highest since 2008. Demand from nuclear power and data centres is rising, but a new mine takes 15 to 20 years to come into operation.

Uranium oxide, or "yellowcake", recovered by processing uranium orePhoto: Dean Calma/IAEA (CC BY-SA 2.0)

The long-term contract price of uranium stood at $98 per pound (0.45 kg) of uranium oxide (U₃O₈) at the end of October 2026, about $216 per kilogram, above the $95 reached in 2007-2008. This is the average of the month-end prices of the uranium market research firms UxC and TradeTech as calculated by Canada's Cameco, and the highest since the long-term price was first tracked in 1996. TradeTech's own assessment puts it at $99. The long-term price has nearly tripled since mid-2021.

Utilities mostly buy uranium under contracts running several years; the spot price is the price for delivery in the near term. In June 2007 the spot price spiked to $136 and then fell sharply; today the long-term price is rising steadily, a sign that buyers expect demand to grow for years. The spot price stood at $91.55 at the end of October.

Uranium long-term and spot prices, 1996-2026Chart: nuclear.mn; source: Cameco

Demand. According to the "Red Book" (Uranium 2026), published jointly by the IAEA and the OECD Nuclear Energy Agency (OECD-NEA), 418 reactors with a combined capacity of 378 GWe were operating worldwide on 1 January 2025, using about 64,500 tonnes of uranium a year. By 2050 nuclear capacity is projected to reach 565-916 GWe, and uranium requirements 84,800-143,900 tonnes a year.

Artificial intelligence is one driver of demand. The International Energy Agency (IEA) estimates that the world's data centres used 415 terawatt-hours of electricity in 2024, 1.5% of global consumption, and will use 945 TWh in 2030, double. Most of the growth is in the United States and China. Nikkei Asia reports that large US technology companies such as Microsoft, Amazon and Google are signing power purchase agreements with nuclear plants, restarting closed ones and investing in small modular reactors. For example:

  • Microsoft: signed a 20-year agreement with Constellation in September 2024 to restart Three Mile Island unit 1 (835 MW), which closed for economic reasons in 2019. This unit is not unit 2, the site of the 1979 accident; it is due to start up again as the Crane Clean Energy Center in 2027.
  • Amazon: agreed with Talen Energy in June 2025 to buy 1,920 MW from the Susquehanna plant in Pennsylvania until 2042. In 2024 it also invested in X-energy and backed a project to build four small modular reactors, 320 MW in all, in Washington State.
  • Google: signed with Kairos Power in October 2024 to buy power from small modular reactors of up to 500 MW in all by 2035, the first due by 2030. In October 2025 it agreed with NextEra Energy to restart the Duane Arnold plant in Iowa (610 MW), closed in 2020, and buy its power for 25 years; it is due back in early 2029.
Data centres' electricity useChart: nuclear.mn; source: International Energy Agency (IEA)

Supply. According to the Red Book, the world's mines produced 61,924 tonnes of uranium in 2024, the highest since 2016 and 96% of that year's reactor requirements. Three countries produce about three-quarters of it: Kazakhstan (38%), Canada (23%) and Namibia (12%). The increase came from restarting idled mines and from existing mines, particularly in Canada, raising their output; no new mine has begun production. Spending on uranium exploration and mine development exceeded $1.78 billion in 2023-2024, about 46% more than in the two years before.

World uranium production, 2022-2025Chart: nuclear.mn; source: Uranium 2026 (Red Book)

Resources. Identified resources recoverable at under $260 per kilogram of uranium ($100 per pound of uranium oxide) exceed 8.1 million tonnes worldwide, enough to meet even the highest projected demand through 2050. But mining projects typically take 15 to 20 years to develop, so the Red Book concludes that advancing new projects in the near term, and adequate prices supported by long-term contracts, are essential to avoid supply disruptions. In resources recoverable at under $130 per kilogram, Australia (29%), Kazakhstan (14%) and Canada (9%) lead.

World uranium resources by countryChart: nuclear.mn; source: Uranium 2026 (Red Book)